Construction

With all subject conditions satisfied on your building agreement and all orders placed, we are in a position to start building your home.

Construction schedule at a glance:

Weeks 1-4  Earthworks, drains, slabs and frames are built.

Weeks 5-8  The house is complete to lock up stage with kitchen installed.

Weeks 9-11  Internal tiling, bathroom fixtures and fittings are installed and the home is painted.

Weeks 12-15   Final painting is completed with electrical and plumbing fittings installed. Carpets and blinds are installed.

Weeks 16-18   Driveways, fences, clothes lines are constructed and installed. Landscaping is completed and the home given a final clean in preparation of handover.

As the home progresses you will be asked to make progress payments at 5 stages as stated in your building agreement. Our team will liaise with you for collection of these payments.

· Base complete 15%

· Frame 20%

· Enclosure 35%

· Fixing 20%

· Practical Completion 5%

(Totalling 100% with a 5% initial deposit)