With all subject conditions satisfied on your building agreement and all orders placed, we are in a position to start building your home.
Construction schedule at a glance:
Weeks 1-4 Earthworks, drains, slabs and frames are built.
Weeks 5-8 The house is complete to lock up stage with kitchen installed.
Weeks 9-11 Internal tiling, bathroom fixtures and fittings are installed and the home is painted.
Weeks 12-15 Final painting is completed with electrical and plumbing fittings installed. Carpets and blinds are installed.
Weeks 16-18 Driveways, fences, clothes lines are constructed and installed. Landscaping is completed and the home given a final clean in preparation of handover.
As the home progresses you will be asked to make progress payments at 5 stages as stated in your building agreement. Our team will liaise with you for collection of these payments.
· Base complete 15%
· Frame 20%
· Enclosure 35%
· Fixing 20%
· Practical Completion 5%
(Totalling 100% with a 5% initial deposit)